PakMEC prepares precise quantity takeoffs and itemized Bills of Quantities that hold up at tender, at negotiation, and on site — so your budget is built on real measurements, not guesswork.
From raw drawings to a fully priced, tender-ready Bill of Quantities — every stage handled with measurable precision.
Trade-by-trade measurement from architectural, structural and MEP drawings — concrete, steel, finishes, and more.
Itemized BOQs formatted to PWD and CSI MasterFormat standards, ready for client approval or tender submission.
Realistic project cost estimates and feasibility budgets to guide investment and financing decisions.
Complete tender packages — technical specifications, conditions of contract, and pricing schedules.
Rate build-up sourced from PWD Schedule of Rates and current market pricing for materials and labor.
Fast, defensible costing for scope changes and site variations during active construction.
Every quantity is measured, priced, and cross-checked against recognized software and rate standards.
A structured six-stage process that turns architectural and structural drawings into a fully priced, tender-ready document.
Reviewing architectural, structural and MEP drawings to define the full scope of measurable work.
Trade-by-trade digital measurement of every quantifiable item — earthwork to finishes.
Applying PWD/market rates and building up unit costs for every BOQ item.
Compiling quantities and rates into a structured BOQ in the client's or tender's required format.
Independent review to verify quantities and pricing against drawings before release.
Delivering the final BOQ with ongoing support through the tendering or bidding process.
Clear item descriptions, units, quantities and rates — laid out the way clients, contractors and tender boards expect.
| Item No. | Description | Unit | Qty | Rate (PKR) | Amount (PKR) |
|---|---|---|---|---|---|
| 1.1 | Excavation for foundation in ordinary soil | Cft | 4,200 | 85 | 357,000 |
| 1.2 | P.C.C. 1:4:8 in foundation | Cft | 1,150 | 430 | 494,500 |
| 1.3 | R.C.C. 1:2:4 in columns & beams | Cft | 2,380 | 1,650 | 3,927,000 |
| 1.4 | Brickwork in superstructure | Cft | 6,900 | 210 | 1,449,000 |
| Sample Subtotal (Illustrative) | 6,227,500 | ||||
* Sample values shown for format illustration only — actual BOQs are project-specific.
From private homes to government tenders, our quantity surveyors adapt format and rate basis to the project.
Homes, farmhouses & housing societies.
Plazas, office towers & retail fit-outs.
Factories, warehouses & production units.
Government projects & competitive bids.
We estimate the way we build — precisely, because our own construction teams work off these same numbers.
BOQs prepared and reviewed by qualified quantity surveyors, not generic spreadsheet templates.
Documents formatted to match public-sector tender requirements and international standards alike.
Pair BOQ preparation with our structural design and construction supervision divisions for one accountable partner.
Still unsure about format, rates, or turnaround? Talk to our quantity surveying team directly.
Talk to a SurveyorSend us your drawings or scope of work — get a preliminary quantity estimate within 48 hours.